Delivering Switchgear Containers for HS2 Project

We worked with CEMA Ltd to deliver specialist switchgear container solutions supporting critical infrastructure works associated with HS2.

The project required highly engineered container housings capable of accommodating complex MCC installations, strict space constraints, and demanding environmental controls. Our off-site container conversion approach enabled safe, controlled build and testing, helping support rapid site redevelopment while minimising risk and disruption.

The Customer

CEMA Ltd was founded in 1987 and is now one of the leading electrical engineering companies in the UK, supplying and installing the highest quality and most advanced process and plant control systems.

The Challenge

To assist rapid re-development of a water abstraction and treatment site necessitated by the HS2 project, CEMA were asked to supply and deliver circa 25M between two Motor Control Centres (MCCs) in separate, re-purposed shipping containers. To bring the requirement to life, CEMA worked with our Conversions team to deliver a best-in-class solution. 

As a consequence of the pandemic, it was agreed to complete all of the build and MCC installation off-site to both minimise travelling and exposure, as well as limiting personnel risk by performing the majority of the work in a controlled environment.

What CEMA Had To Say

“S Jones presented themselves and their capability far in excess of their competitors. Their understanding of the client requirements and the attention to detail was paramount to the success of the project. Working directly with Andrew and Les meant we had direct access for timely and knowledgeable decisions and guidance. We would highly recommend S Jones for all partners on future schemes.”

Graeme Morley, Managing Director – CEMA Ltd

Two 40ft shipping containers combined to form a switchgear enclosure, showing a green containerised plant room with personnel access door, external cable connections, safety fixtures and integrated access walkway for electrical infrastructure installations.

Need a Fire-Rated, Purpose-Built Enclosure for Critical Operations?

We design and deliver bespoke containerised enclosures for control rooms, operator cabins, and safety refuges within high-risk industrial and infrastructure environments. Engineered to meet stringent fire protection and access requirements, our container conversions provide robust solutions where safety is paramount.

Learn more about our container conversion capabilities or contact us today to discuss your project.